Confidential client
Onshore Gas Lift Piping Network Installation and Connection Support
36 km dual 4-inch underground RTP piping network
Location: Saudi Arabia
Operator: Confidential
Duration: 2024
Scope: Piping network installation and well connection for gas lift operations
We provided detailed engineering services for the design and installation of a 36 km dual 4-inch underground RTP piping network for a Gas Lift Ring. Our expertise ensured the seamless connection of 12 manifolds and 14 wells to the Gas Lift Ring, which links to an existing Gas and Oil Separation Plant (GOSP) through a designated manifold, optimising gas lift operations.
Scope:
- Installation of a 36 km dual 4-inch underground RTP piping network
- Connection of 12 manifolds to the Gas Lift Ring
- Integration of 14 wells into the Gas Lift Ring
- Connection of the Gas Lift Ring to the GOSP via a designated manifold